Heathrow Express Extension – Terminal 5 | UK

Project summary:
Monitoring of the existing express rail tunnel during construction of the new tunnel
Location
london bridge
Period of the service
2004-2005
Sixense solutions used
TO DO MAP

A new link rail link for Terminal 5

Heathrow Express is an airport rail link between London Heathrow Airport and London Paddington station. The service opened in 1998 and is operated by the Heathrow Express Operating Authority, a wholly owned subsidiary of Heathrow Airport Holdings Limited.

 

As part of the extension works at Heathrow Airport, Terminal 5 is to be linked to the existing terminals via the Heathrow Express.

 

 

Sixense appointed

Sixense were appointed to carry out the installation and monitoring to the existing Heathrow Express running tunnel between Terminals 3 and 5 during the passage of the tunnel boring machine into the existing turnout stub, and during breakout into the existing tunnel.

 

A comprehensive monitoring system was installed. This comprised of:

 

 

  • 120 Nos. Prisms (Automated Monitoring)

 

  • 80 Nos. Prisms (Manual Monitoring)

 

Real-time movements were monitored and recorded on Sixense’s Geoscope monitoring software. Both Cyclops instruments were driven by a computer installed in the baggage area and linked to the instruments by a data cable running along the tunnel lining.

 

Another computer was installed in the contractor’s control room and linked to the baggage area via a modem. This allowed the monitoring engineer and contractor to assess and review movements of the tunnel in real time.

 

A remote alarm system was also installed within the Heathrow Express control room and linked to the monitoring engineer’s PC via a phone line. This alarm system would activate a flashing warning light if triggers were breached, allowing the control room staff to stop train movements immediately and ensure passenger safety.

 

Terminal 5 opened on 27th March 2008 and the full Heathrow Express service to T5 opened on 23rd June the same year.

Images of the project

2

Nos. Automated Total Stations

120

Nos. Prisms

80

Nos. manually read prisms

24

Hours attendance during critical phases of TBM passage

Similar projects

Geographic Area

Geographic area

GEOGRAPHIC AREA text to fill Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin dignissim orci dui, eu efficitur lectus feugiat ut.

Browse Projects in Europe
Geographic Area

Sector segment

MARKET SEGMENT text to fill Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin dignissim orci dui, eu efficitur lectus feugiat ut.

Browse Projects in Airports Browse Projects in Tunnels
Geographic Area

Sixense offers

SIXENSE OFFERS Description text to fill Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin dignissim orci dui, eu efficitur lectus feugiat ut.

Browse Projects in Monitoring